Selasa 06 Nov 2018 22:43 WIB

JK wants 300 houses built each day in Lombok

JK targeted reconstruction in Lombok can be completed by March 2019

New houses built for quake victims in Kekait Village, Gunungsari, West Lombok, West Nusa Tenggara.
Foto: Antara/Ahmad Subaidi
New houses built for quake victims in Kekait Village, Gunungsari, West Lombok, West Nusa Tenggara.

REPUBLIKA.CO.ID, JAKARTA -- Vice President Jusuf Kalla has instructed his staff to speed up the reconstruction process after the earthquake disaster in Lombok, West Nusa Tenggara. He expected it could be completed within six months.

"Actually, the point is acceleration. Each day, only 40 units of the house are produced. I call on the staff to increase the number to 300 (units) each day, so that we can complete it in six months," Kalla told reporters at the Vice President's Office on Tuesday.

The series of earthquakes that struck Lombok on July 29 damaged 167 thousand housing units; 1,194 schools; 321 health facilities; and 1,091 houses of worship, according to data from the National Disaster Management Agency (BNPB).

Funds that have been budgeted by the Government, through the APBN for the reconstruction of Lombok, reach Rp1 trillion. According to Kalla, the figure is still increasing as needed.

"The funds disbursed have reached Rp1 trillion and there is still a need for more funds. But construction has begun, and it requires acceleration," Kalla explained.

Also read: Construction of houses in Lombok to take 8 months: Kalla

Kalla, as the Disaster Management Commander, hopes that post-disaster reconstruction and rehabilitation in Lombok can be completed by March 2019, six months faster than the previous target, which is one year since the earthquake occurred, or in July 2019.

Community health and safety are a concern, because there are limits on how people can live and move in refugee camps. According to the vice president, if people live in refugee camps for more than six months, it might lead to health problems and social problems.

"The Regional Government and all parties involved must make a time schedule and set targets to complete it. "It is expected to be completed by March 2019, so that people can return to occupy their respective homes," he added.

The need for production of earthquake-resistant home applicators must also be recalculated, so that the amount of production can be adjusted. In addition, the involvement of technical students must also be maximized to accelerate the construction of new housing for the community.

sumber : Antara